December 2021

Building Activity Summary December 2021
Uncertified Building Permits 22
Certified Building Permits 84
Building Approval Certificates 1
Demolition Permits 3
Total 110
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
4.62
Building Permit Processing time - Uncertified Applications
Legislative Time Frame:25 Working Days (Average number of days)
10.41

November 2021

Building Activity Summary November 2021
Uncertified Building Permits 57
Certified Building Permits 104
Building Approval Certificates 8
Demolition Permits 5
Total 174
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
4.51
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
13.70

October 2021

Building Activity Summary October 2021
Uncertified Building Permits 17
Certified Building Permits 84
Building Approval Certificates 4
Demolition Permits 11
Total 116
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
5.74
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
15.71

September 2021

Building Activity Summary September 2021
Uncertified Building Permits 46
Certified Building Permits 111
Building Approval Certificates 5
Demolition Permits 13
Total 175
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
5.30
Building Permit Processing time - Uncertified Applications
Legislative Time Frame:25 Working Days (Average number of days)
13.67

August 2021

Building Activity Summary August 2021
Uncertified Building Permits 37
Certified Building Permits 100
Building Approval Certificates 4
Demolition Permits 6
Total 147
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
6.06
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
17.65

July 2021

Building Activity Summary July 2021
Uncertified Building Permits 26
Certified Building Permits 111
Building Approval Certificates 5
Demolition Permits 9
Total 151
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
6.71
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
17.96

June 2021

Building Activity Summary June 2021
Uncertified Building Permits 51
Certified Building Permits 137
Building Approval Certificates 1
Demolition Permits 9
Total 198
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
6.01
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
17.39

May 2021

Building Activity Summary May 2021
Uncertified Building Permits 45
Certified Building Permits 161
Building Approval Certificates 3
Demolition Permits 5
Total 214
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days(Average number of days)
6.71
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
17.87

April 2021

Building Activity Summary April 2021
Uncertified Building Permits 43
Certified Building Permits 119
Building Approval Certificates 0
Demolition Permits 9
Total 171
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
7.28
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
18.12

March 2021

Building Activity Summary March 2021
Uncertified Building Permits 34
Certified Building Permits 121
Building Approval Certificates 1
Demolition Permits 4
Total 160
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
6.26
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
13.18

February 2021

Building Activity Summary February 2021
Uncertified Building Permits 57
Certified Building Permits 100
Building Approval Certificates 2
Demolition Permits 3
Total 162
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
5.93
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
15.96

January 2021

Building Activity Summary January 2021
Uncertified Building Permits 63
Certified Building Permits 111
Building Approval Certificates 4
Demolition Permits 8
Total 186
Building Permit Processing time - Certified Applications
Legislative Time Frame: 10 Working Days (Average number of days)
6.25
Building Permit Processing time - Uncertified Applications
Legislative Time Frame: 25 Working Days (Average number of days)
17.84