December 2022
Building Activity Summary |
December 2022 |
Uncertified Building Permits |
44 |
Certified Building Permits |
80 |
Building Approval Certificates |
9 |
Demolition Permits |
4 |
Total |
137 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
5.90 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
14.05 |
November 2022
Building Activity Summary |
November 2022 |
Uncertified Building Permits |
30 |
Certified Building Permits |
80 |
Building Approval Certificates |
1 |
Demolition Permits |
8 |
Total |
119 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
5.17 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
15.97 |
October 2022
Building Activity Summary |
October 2022 |
Uncertified Building Permits |
20 |
Certified Building Permits |
83 |
Building Approval Certificates |
3 |
Demolition Permits |
8 |
Total |
114 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.92 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
18.05 |
September 2022
Building Activity Summary |
September 2022 |
Uncertified Building Permits |
20 |
Certified Building Permits |
83 |
Building Approval Certificates |
32 |
Demolition Permits |
3 |
Total |
108 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.35 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
16.65 |
August 2022
Building Activity Summary |
August 2022 |
Uncertified Building Permits |
26 |
Certified Building Permits |
96 |
Building Approval Certificates |
3 |
Demolition Permits |
6 |
Total |
131 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.77 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
18.11 |
July 2022
Building Activity Summary |
July 2022 |
Uncertified Building Permits |
25 |
Certified Building Permits |
97 |
Building Approval Certificates |
5 |
Demolition Permits |
4 |
Total |
131 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.85 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
19.27 |
Â
June 2022
Building Activity Summary |
June 2022 |
Uncertified Building Permits |
30 |
Certified Building Permits |
93 |
Building Approval Certificates |
1 |
Demolition Permits |
1 |
Total |
125 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.81 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
17.63 |
May 2022
Building Activity Summary |
May 2022 |
Uncertified Building Permits |
45 |
Certified Building Permits |
101 |
Building Approval Certificates |
2 |
Demolition Permits |
4 |
Total |
152 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
6.25 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
17.33 |
Â
April 2022
Building Activity Summary |
April 2022 |
Uncertified Building Permits |
19 |
Certified Building Permits |
92 |
Building Approval Certificates |
3 |
Demolition Permits |
3 |
Total |
117 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
5.76 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
16.95 |
Â
March 2022
Building Activity Summary |
March 2022 |
Uncertified Building Permits |
47 |
Certified Building Permits |
113 |
Building Approval Certificates |
7 |
Demolition Permits |
7 |
Total |
168 |
Building Permit Processing time – Certified Applications Legislative Time Frame – 10 Working Days – (Average number of days) |
5.37 |
Building Permit Processing time – Uncertified Applications Legislative Time Frame – 25 Working Days – (Average number of days) |
16.63 |
Â
February 2022
Building Activity Summary | February 2022 |
Uncertified Building Permits | 19 |
Certified Building Permits | 65 |
Building Approval Certificates | 2 |
Demolition Permits | 5 |
Total | 91 |
Building Permit Processing time - Certified Applications Legislative Time Frame: 10 Working Days (Average number of days) |
6.59 |
Building Permit Processing time - Uncertified Applications Legislative Time Frame: 25 Working Days (Average number of days) |
19.84 |
January 2022
Building Activity Summary | January 2022 |
Uncertified Building Permits | 28 |
Certified Building Permits | 58 |
Building Approval Certificates | 4 |
Demolition Permits | 6 |
Total | 96 |
Building Permit Processing time - Certified Applications Legislative Time Frame: 10 Working Days (Average number of days) |
5.93 |
Building Permit Processing time - Uncertified Applications Legislative Time Frame:25 Working Days (Average number of days) |
18.83 |