The City of Gosnells administers Development Contribution Plans for the shared provision of infrastructure and the acquisition of land for public purposes in the Canning Vale, Homestead Road, Maddington Road Precincts A and B, Central Maddington, Southern River Precinct 1, Southern River Precinct 2 and Southern River Precinct 3 Outline Development Plan areas. The Development Contribution Plan Reports for these areas are reviewed annually.
Development Contribution Areas - Rates 2024/25
| Development Contribution Area | Development Contribution Rate 2024/25 (as at April 2025) | Public Open Space Rate (as at April 2025) | Infrastructure Works (for more detail refer to Local Planning Scheme No. 24) |
|---|---|---|---|
| DCA 1 - Canning Vale | $78,025 per ha | $2,000,000 per ha | Drainage construction; shared paths; road construction and resumption; traffic management; service relocation and power line upgrading; Conservation Category Wetland development. |
| DCA 2 - Southern River Precinct 2 | $125,800 per ha | $1,400,000 per ha | Drainage construction; land acquisition and construction of arterial roads; traffic management; land acquisition and development of Conservation Category Wetlands. |
| DCA 4 - Central Maddington Precinct 1 | R20 - $375,505 per ha R30 - $563,257.50 per ha R40 - $751,010 per ha R80 - $1,502,020 per ha | R20 - $191,450 per ha R30 - $287,175 per ha R40 - $382,900 per ha R80 - $765,800 per ha | Drainage construction; shared paths; land acquisition and construction of roads; traffic management; street lighting and underground power; street trees and development of Public Open Space. |
| DCA 4 - Central Maddington Precinct 2 | R20 - $133,695 per ha R30 - $200,542.50 per ha R40 - $267,390 per ha | R20 - $191,450 per ha R30 - $287,175 per ha R40 - $382,900 per ha | |
| DCA 5 - Maddington Road Precinct A | $154,300 per ha | $1,250,000 per ha | Acquisition and development of Public Open Space |
| DCA 5 - Maddington Road Precinct B | $119,400 per ha | $1,250,000 per ha | |
| DCA 6 - Southern River Precinct 1 | $110,600 per ha | Not applicable | Land acquisition and upgrades of arterial roads; traffic management devices; fauna underpasses; land acquisition and construction of roundabout and Holmes Street and Harpeden Street. |
| DCA 7 - Homestead Road | $241,000 per ha | $107.32 per m2 | Construction of drainage upgrade; construction of roundabouts and shared use path; construction of drainage detention basin; acquisition and development of Public Open Space. |
| DCA 8 - Kenwick South | Draft DCP adopted in 2017, final DCP not yet adopted - please contact the City for information | Draft DCP adopted in 2017, final DCP not yet adopted - please contact the City for information | Construction of roads, roundabout and footpath; water main upgrade; development of Public Open Space; interim drainage and construction of drainage detention basin. |
| DCA 9 - Southern River Precinct 3 (SR P3) | $187,217.48 | $1,450,000 per ha (urban) $350,000 per ha (rural) $451,000 per ha (site specific) | Drainage; acquisition and upgrades for arterial roads; traffic management devices; shared use paths; development of Public Open Space; relocation of services. |
| SR P3 sub-precinct 3A North | $17,362.65 per ha | $244,184.65 per ha | |
| SR P3 sub-precinct 3A South | $9,533.14 per ha | Not applicable | |
| SR P3 sub-precinct 3D | $29,419.80 per ha | Not applicable | |
| SR P3 sub-precinct 3E | $9,111.17 per ha | $100,070.73 per ha |